This project involves a cooling and air filtration system for a new workshop for a pharmaceutical factory located in Wuwei City, Gansu Province, within the Wuwei Industrial Zone, Liangzhou District, Gansu. The project includes a large intravenous infusion workshop, injection molding machines, mold cooling and blowing systems, and a purified air conditioning system for the capsule and pellet workshop. Additionally, it incorporates cooling processes such as sterilizing the workshop and preparing purified water. As per the production process requirements, this design covers air conditioning for clean workshops, comfort air conditioning (cooling and heating), and cooling systems for production lines.
Project Requirements
Item | Cooling Area | Heating Area | Summer Cooling Requirement | Winter Heating Requirement | Cleanliness | Cooling Load | Heating Load |
1 | Tablet and pellet area | 400㎡ | 24 ± 2℃ | 18 ± 2℃ | Class D | 170kw | 100kw |
2 | Large infusion workshop | 700㎡ | 24 ± 2℃ | 18 ± 2℃ | Class C | 280kw | 175kw |
3 | Sterilization and dressing room | 1000㎡ | 24 ± 2℃ | 18 ± 2℃ | - | 146kw | 82.5kw |
Total | 995kw | 595kw |
System Design